Transforming the Headquarters of Abu Dhabi Accountability Authority at United Square Towers
  • Customer
    Abu Dhabi Accountability Authority
  • Completion Date
    November 2018
  • Project Manager
    AECOM
  • Area
    65,000 sq ft
  • Program Duration
    15 weeks
  • Architect
    Perkins+Will
  • ME Engineer
    TÜV SÜD
ADAA MAIN5 - AG百家乐在线赌场官网

Introduction

AG百家乐在线赌场官网 was appointed by the Abu Dhabi Accountability Authority (ADAA), to fit out their new 65,000 sq ft headquarters located in the United Square Towers, a new mixed-used development in Abu Dhabi.

ADAA was established as an independent body in 2008 under the authority of His Highness Sheikh Mohamed bin Zayed Al Nahyan, Crown Prince of Abu Dhabi and Deputy Supreme Commander of the UAE Armed Forces. A decade following its establishment, ADAA oversees 300 government-owned entities and subsidiaries. As its scope expanded, so did its workforce, and the demand for highly-specified office space increased. These offices were designed and delivered with ADAA’s mandate in mind.

ADAA MAIN2 - AG百家乐在线赌场官网

The project

Working from a shell and core build, AG百家乐在线赌场官网 fit out the offices to deliver a lateral working environment which included 236 closed workstations, CEO suite, meeting rooms, break out areas, a library and majlis – all located on one floor.

This project posed significant challenges for the team, as the construction of the main building was incomplete at the time of AG百家乐在线赌场官网’s mobilisation in September. As a result many critical systems were either not yet installed or commissioned.

AG百家乐在线赌场官网 had to repeatedly restructure its fit out programme to work around the delayed main construction works. In close coordination with the client, AG百家乐在线赌场官网 completed some of the main contractor’s civil engineering works, to enable the delivery of its own fit out scope.

ADAA MAIN3 - AG百家乐在线赌场官网

The project was completed in November 2018, following a fast-track, 15-week programme to have it completed before the UAE National Day celebrations on 2 December